Project Description
The project limits consist of Grants Settlement Road from Foresters Falls Road (CR-7) to McCoy Road.
The 6.44 km rehabilitation project scope of work consists of the following:
Status
Planning Stage
Schedule
The existing double surface treatment will be removed in June. The replacement of culverts, ditching, granular base, and double treatment surface is scheduled to start in June and be completed by September.
Notices
Future notices will be sent to property owners along the project area.
Funding
The Council of the Township of Whitewater Region has included the rehabilitation of Grants Settlement Road in the 2025 budget, funded by the Ontario Community Infrastructure Fund (OCIF) and taxation.
Map
Project Contact
Kyle Eady
Road Superintendent
Township of Whitewater Region
613-646-2282 ext. 152
keady@whitewaterregion.ca