Project Description
The project limits consist of Kohlsmith Road from Kerr Line to Queens Line (CR-4).
The 2.8 km rehabilitation project scope of work consists of the following:
Status
Complete
Schedule
The removal of the existing double surface treatment will take place at the end of May. Replacement of culverts, ditching, granular base and double treatment surface is scheduled to start in June and be completed in July.
Notices
Future notices will be sent to property owners along the project area.
Funding
The Council of the Township of Whitewater Region has included the rehabilitation of Kohlsmith Road in the 2024 budget, funded by the Ontario Community Infrastructure Fund (OCIF) and Canada Community Building Fund (CCBF).
Map
Project Contact
Kyle Eady
Road Superintendent
Township of Whitewater Region
613-646-2282 ext. 152
keady@whitewaterregion.ca