Project Description
The project limits consist of Sutherland Road from Highway 17 to Snake River Line.
The 1.35 km rehabilitation project scope of work consists of the following:
Status
Design Phase
Schedule
The removal of the existing double surface treatment will take place at the end of May. Replacement of culverts, ditching, granular base is scheduled to start in July and be completed in August.
Notices
Future notices will be sent to property owners along the project area.
Funding
The Council of the Township of Whitewater Region has included Sutherland Road in the 2024 budget, funded by the Ontario Community Infrastructure Fund (OCIF).
Map
Project Contact
Kyle Eady
Road Superintendent
Township of Whitewater Region
613-646-2282 ext. 152