Rehabilitation of Cameron Street, Earl Street, and Vera Crescent

Project Description

The project area includes approximately 1.2km of road rehabilitation in Beachburg.

  • Cameron Street from Beachburg Road (County Road 21) to Vera Crescent
  • Earl Street from Cameron Street to Cardel Street
  • Vera Crescent

The construction work proposed includes grading, granular base, hot mix paving, concrete curb and gutter, concrete sidewalk, storm sewers, water system, and landscaping.

Contractor: H&H Construction Inc.
Contract Adminstrator: Jp2g Consultants Inc. 

Status

Complete

Schedule

A deficiency review will take place in the spring of 2024.

Water Outages

Water Outage Map - August 25th
Water Outage Map - August 23th
July 7th Water Outage - Update
Water Outage Map - July 7th
Water Outage Map - July 4th & 6th

Notices

June 30, 2023
June 21, 2023
May 8, 2023
November 6, 2022
November 2, 2022
October 14, 2022
August 31, 2022
August 24, 2022
August 22, 2022
June 7, 2022
June 5, 2022
June 3, 2022
June 9, 2022
Pre-Construction Survey
April 14, 2022

Funding

Council of the Township of Whitewater Region has funded the rehabilitation of Cameron Street, Earl Street, and Vera Crescent in the 2022 budget through a long-term debenture.

Public Involvement

The public information session will be held on:
Date: Thursday, April 21, 2022
Time: 6:00 pm to 8:00 pm
Location: Cobden Arena (Upstairs Hall), 43 Astrolabe Rd, Cobden

Comment Sheet
Plan and Layout

Key Map

Project Contact

Lane Cleroux
Manager of Public Works
Township of Whitewater Region
P.O. Box 40, 44 Main Street Cobden, ON K0J 1K0
Phone: 613-646-2282 ext. 128
Email: lcleroux@whitewaterregion.ca