Project limits: Pappin Road from Beachburg Road (County Road 21) to Zion Line.

The 2.5km rehabilitation project scope of work consists of the following:

  • Removal of double surface treatment
  • Culvert replacement
  • Minor ditching
  • Road raising in low laying areas
  • New granular base material
  • Installation of a hard surface

Status

Completed

Schedule

The project will be completed by Township staff and double surface treatment will be removed during the week of May 30th. 

The construction will take place during the month of June with the hard surface completed this summer.