Zion Line Rehabilitation

Project Description

Project limits: Zion Line from Beachburg Road to Hila Road.

The 3.2km rehabilitation project scope of work consists of the following:
2022

  • Removal of double surface treatment
  • Culvert replacement
  • Ditching and drainage improvements
  • ​New granular material

​2023

  • Installation of a hard surface

Status

Complete

Schedule

Double Surface treatment is scheduled for the week of July 3rd, 2023

Notices

May 26, 2022

Funding

The 2022 scope of work for the Zion Line rehabilitation project is being funded by Township’s capital reinvestment reserve.

Project Contact

Lane Cleroux
Manager of Public Works
Township of Whitewater Region
P.O. Box 40, 44 Main Street Cobden, ON K0J 1K0
Phone: 613-646-2282 ext. 128
Email: lcleroux@whitewaterregion.ca